The news you’ve been looking for! The Northeast and Southeast Quadrants of Washington Square Park opened today, Thursday, June 2nd! This will complete Phase II – A, a large section of the park, the entire eastern side, which has been under construction for 20 months. PHOTOS COMING!
Phase II was scheduled for completion by Fall 2010; then we heard the end of the year (tho’ doubted it), then “Spring 2011,” then “by Memorial Day,” but park goers looked happy to be finally able to stream through the eastern end of the park.
Of course, this isn’t all of Phase II, since, for one, part of it (The Mounds and the Large Dog Run) was moved into Phase III. And Chess Plaza, technically still in Phase II, now Phase II-B, won’t be finished til the end of the month. At least, at last, it’s something!
WSP Blog chronicled the problems back in September 2010 outlining how the city’s parks department caused numerous delays in getting the job done, how the project was over-budget, and the fact that no governmental agencies were providing oversight.
Washington Square Park’s entire redesign – Phases I, II, and III – was budgeted and approved for $16 Million at the onset. Phase I alone — which moved the fountain to align with the Arch, reduced the public space around the fountain, and re-landscaped the NorthWest Quadrant, opened in May of 2009 — cost $13 Million. Phase II was budgeted at $9 Million but will likely be $8 Million and that’s without the Large Dog Run and Mounds (included in the original figure). Phase III (rest rooms and administrative building – the new “pergola”) had been budgeted at $9 Million (note – that’s before the cost of the Mounds and Dog Run are added in). (Got all that?)
Since the Parks Department’s projects continue to be seriously over-budget with no apparent oversight by any governing body, the project by the end will have more than doubled from its approved budget and is now projected for $30-$35 Million in cost.
The fountain is out from under wraps but not on yet – in case you were wondering.