What follows are some of the highlights from yesterday’s (April 14) Landmarks Preservation Commission meeting, a continuation of the
March 17th public hearing, scheduled to determine what the future holds for Phase II of Washington Square Park’s redesign by New York City’s Parks Department. So here goes…
* The number of seating alcoves in the Park
There’s actually some good news. Which is that the New York City Parks Department, responding to the calls from Council Member Alan Gerson, Community Board 2, and impassioned park goers to keep their hands off Washington Square Park‘s popular seating alcoves, increased the number in their plan from two to four. The Park currently has six. So, that’s … something.
The Parks Department, represented by Charles McKinney and designer George Vellonakis, started out stating that they were prepared to add one or two more alcoves to the originally proposed two. However, they preferred three. George Vellonakis said that ideally a fourth would be omitted because its location inside the Park lawn on the (south) east side “distracts the view and expansion of the lawn.” The other reasons given by Mr. Vellonakis for omitting that fourth alcove were possible damage to surrounding tree roots and that that area in the new design undergoes a “geometry change.”
At first, Robert Tierney, LPC chair, advocated for the 3 alcoves as he believed that was the Parks Department’s “preference.” The Parks Department stated that the fourth alcove would be very small and “intimate” but how small I’m not sure.
Thankfully, the heroine of the meeting, Commissioner Roberta Brandes Gratz, stood her ground and argued repeatedly for the fourth. She said, “There was a lot of controversy about the redesign – for many legitimate reasons. This park evolved with many layers of change and use which took it away from the original more pristine design. This park is not like Gramercy Park. The park evolved with the neighborhood.” She also said, “I’m not concerned if a piece of lawn is taken away. It’s about how the park is used and the weight of its importance and use outweighs the difficulty of it intruding on [tree] roots.”
It was Ms. Brandes Gratz’s persistence and unwavering that convinced the rest of the Commissioners of the importance of the four (vs. three) alcoves. The inclusion of these four adds to (and maintains) the Park’s charm and uniqueness and gives us a bit of a break from all the symmetry of Phase I.
* Increased seating? Depends what year within the Park’s history you base this on
The Parks Department claims that seating is being “increased by 37%.” George Vellonakis stated that there are currently 355 benches and there will be 487 benches in the newly designed version. (These numbers do not include benches being added into the new alcoves.) However, Park advocate Jonathan Greenberg walked with me around the park recently and he informed me that the Parks Department has been consistently removing benches over the years. (Why…? I don’t know.)
So, to truly determine what the increase would be, you’d have to calculate from an older number of existing benches from a previous year (1970 perhaps?).
In fact, if you walk around each alcove as well as the Northeast corner where the picnic tables are, you will see iron or metal ‘holders’ on the ground that indicate where the benches previously were located that have been removed. (I’m going to write a separate post on this.)
* The Stage – Garibaldi Plaza – Shrunken, Relocated, No Guardrail but Approved
The performance area – the newly named Garibaldi Plaza (previously “Teen Plaza”) – was very quickly discussed at the meeting and it’s unclear to me if any changes were made from the previous version shown. The stage is moving and shrinking and has no guardrails and basically no backstage, if it’s the same version last presented.
Again, Commissioner Roberta Brandes Gratz asked pointed questions such as “you moved the stage because…?” and “Is it better than the old stage?” and “Will you have a backstage?” To this last question, George Vellonakis said that the “[performance] groups will assemble in this pathway” and pointed to an area that I could not see from where I was. (I left Mr. Vellonakis a message to clarify and will update if I receive the answer.)
I think there may be a plan for a temporary railing to prevent the conductor or performers from, um, falling off the stage.
The Washington Square Music Festival testified at the last meeting calling for approval of the plan while simultaneously expressing their disapproval. Although this group only uses the area about five times a year, they are considered sort of the arbiter of the space, so their lukewarm “support” in a sense sealed the deal.
* The Vote – Plan Approved
Before the vote, another LPC Commissioner Christopher Moore referred to the testimony given at the March 17th hearing as “heartfelt and passionate” and intimated that that testimony should be respected. He also said he liked the addition of the fourth alcove because it added to the Park’s “idiosyncratic quality.”
The plan was approved unanimously with the intention that the lights, fence, and pathways will be restored in keeping with Phase I’s work, the stage will be moved and reconfigured, and that there will be four seating alcoves retained within the Park.
* The Past is Our Future
But, of course, it was the first set of Landmarks Preservation Commission hearings in May 2005 where the crucial decisions were made to approve the sweeping changes proposed by the Parks Department to reconfigure Washington Square Park.
It is widely alleged, that, at that time, the Commissioners were pressured by Mayor Bloomberg’s office to go along with an approval and information was leaked to the New York Times in advance that they were going to do so. An article appeared in the Times the morning of the critical vote signaling the Commission would be going along with the Parks Department’s plan.
****************************************************************
* Video here of Q&A from the original Landmarks Preservation Commission hearing – May 10, 2005 by Matt Davis (who directed the work-in-progress documentary “SQUARE: Straightening Out Washington Square Park”). New York State Supreme Court Judge Emily Jane Goodman later ruled that “essential elements of the Parks Department’s plans … were not adequately revealed to Community Board 2 or the Landmarks Commission…”
It would be great if they could keep the current fencing so that people can use it for sitting, as they do now. Also, the current fencing is standard in almost every park in the city, so it doesn’t make sense that WSP is getting the spiked fencing.
Praise be to Commissioner Roberta Brandes Gratz for her stand in redirecting the Phase II design proposals toward stated community needs. Another community need I feel is getting very short shrift in Phase II is the PERFORMANCE STAGE. Its design and location should be restudied, especially in the light of potentially expanding long-range uses of the park, and in line with the recommendations envisioned by many park-use evaluations. For instance, in past seasons, attending musical performances at Teen Plaza, one must contend with competition from being seated in the middle of a crossroads, limited stage area, no accoustical baffles or wind (or even slight, provisional weather) protection, etc., and Phase II envisions even more compromised conditions. Why can’t a STATE OF THE ART PERFORMANCE STAGE be insisted on as a FOCUS and (geometric, if that’s the winning buzzword) FEATURE of that axis of the park, not a badly-served and watered-down afterthought? Wouldn’t this be an essential part of a long-range plan to underscore the park’s continued and expanding viability as a performance venue?