Checking in on Washington Square Park Redesign: Phase II —
September is around the corner and while Phase II-A – the entire Eastern end – finally opened a few months ago in early June; the remainder, Phase II-B, the Southwestern Quadrant which includes the Chess Plaza, is still lagging far behind.
Lately, it looks like the work has stalled. Are the same issues that I first reported one year ago still occurring now? One thing is certain, the absence of oversight by any city governing agency continues.
While neglecting to provide a reason for the prolonged delay, Parks Department spokesperson Phil Abramson pointedly commented that the construction will be finished “by end of summer” which he clarified “is mid/late September.” The Parks Department web site says Fall 2011.
WSP’s Phase II construction: A story of moving parts and roving completion dates
Washington Square Park Redesign: Phase II originally included the entire Northeast and Southeast side as well as the Southwest Quadrant of the Park including the Chess Plaza, Mounds, Large Dog Run and Perimeter Sidewalks.
These last three areas have been removed from Phase II entirely (moved into Phase III) although, all of Phase II, with these sections included, was initially scheduled to be completed by Fall 2010. That date then moved to December (tho’ I doubted it); next came word of Spring 2011. After this, Phase II was split into two parts with the city’s Parks Department reporting that the Eastern end was scheduled to open “around Memorial Day.” That date was pretty close to being realized — Phase IIA opened June 2nd of this year.
Phase II B was supposed to follow a similar trajectory. In April, it was announced that its completion was scheduled “in June,” to follow close on the heels of the Eastern side. However, as the SW section dragged behind, the date changed to “August 8th,” and now, as you see, the official word is end of September.
As a relatively small section of the park, what could be the hold up? Some days there’s barely any work done and yet two Fridays ago, there was much action with numerous workers and multiple trucks (that was the day the trees were removed). At that time, it seemed like the work could be completed momentarily. Since then, not so much.
Will people be able to actively use Chess Plaza again this year? Will the London Plane tree in the Plaza survive?
As you see, questions remain with no concrete answers.
**************************************************************
Coverage Close to One Year Ago at WSP Blog:
Part I – Washington Square Park Phase II: An Eerie Silence – What’s Going On? September 1, 2010
Part II – Washington Square Park Phase II: Lack of Transparency & Oversight Continues September 7, 2010
Phase II Parks Department WSP construction signs — “Working to Improve Your Park” —