Among Other Things, Phase II Contractor Confirms WSP Fountain is Not Aligned with the Arch After All (Part II)

Oh Dear...

Updated 3:45 p.m. — I’ve written here about the problems and certainly the delays on Washington Square Park’s redesign over the last few years. Now it has been confirmed that the stalled work on Phase II, halted for six weeks now, is due to a dispute between the city’s Parks Department and the contractor, Tucci Equipment Rental Corporation. Anthony Martucci, the head of Tucci, says that the Parks Department has not paid him a large sum he is owed and is cutting payment amounts for work for which costs were approved in advance by the city agency.

In an email to Parks Commissioner Adrian Benepe, Community Board representatives, City Council members, and select press this week, Martucci says that he agreed to a “gag order” after speaking out last fall about problems at the park (see this post from September 2010 for some details of the problems at that time). He says he came to an agreement at that time with the Parks Department and the relationship was relatively harmonious for awhile. That harmony ended at some point earlier this year.

In his email, Martucci outlines some significant pieces of information. Perhaps the one of most interest relates to the aligning of the fountain with the Arch.

A little history of WSP Blog coverage on this topic — I wrote about this possible misalignment in August 2008 and also after a reader, Steve, commented in August 2009, as follows:

Is anyone ever going to admit that the fountain is now aligned to nothing — not the center of the park as it was before, not the arch and not 5th Avenue? What was the point of moving it?!?!?! It is NOT aligned to either the arch or the avenue.

The Bloomberg Administration’s grand “vision” for Washington Square Park included moving the Fountain from its historic location to a new placement 22 feet east so it would align with the Arch at Fifth Avenue. Pretty much no one agreed with this change in location but the administration would not be deterred.

The fountain had been in its previous location – which was the actual CENTER OF THE PARK – since 1871; over 137 years, until Mayor Michael Bloomberg became in charge.

The Parks Department claimed that it would not cost any additional money to construct the fountain in a new location — a new location which involved rerouting water lines — but that is up for much debate and likely untrue – an obfuscation of the truth. Moving water lines would have to add additional costs.

In 2007, community activist Jonathan Greenberg hired a company to assess the costs of moving the Fountain and presented the findings to Council Member Alan Gerson. The company’s assessment was that it would cost at least $500,000 to move the Fountain. Gerson queried the Parks Department about this and the agency insisted there was no additional cost involved and the former Council Member took them at their word. It was one last try, after ongoing attempts to persevere by the community, to get the fountain location move stopped, as even the Landmarks Preservation Commission caved to Bloomberg’s wishes (and tactics).

From Martucci’s email:

So Tucci did some investigating, found out the center of the fountain was actually 4 ft out from the center. This threw all the designers dimensions off, and Parks knew it but didn’t tell Tucci because they didn’t want to let the public know.

When Tucci exposed this, Parks to protect them self was going to default Tucci from the project.

I have fought very hard to finish this job, Tucci hasn’t gotten paid now for 3 months, and just recently parks has cut payment 13 from $650,000 to $276,000 without explanation.

That is one reason the chess plaza was stalled last year — remember when a tree was in the way of the planned curb? It seemed at the time like a small error which the Parks Department and contractor could not come to an agreement on how to resolve. Actually it was due to a BIGGER ERROR – the mis-aligning of the Fountain. (And, as we know, other errors have caused casualties such as the repeatedly dying trees around the fountain — young trees which replaced perfectly healthy 40 year old trees in the original location.)

What else has this thrown off?

Does this just confirm that, after all, the famous Washington Square Park Fountain could have been left in its well-liked and historic original location as the “mid-point” of the park?

***********************************************************************

Previously on WSP Blog:

* Wouldn’t it be ironic if – after everything – the Washington Square Park Fountain was still off-center to the Arch? August 7, 2008

* So … *is* the Washington Square Park Fountain aligned to the Arch? August 10, 2009

* Actually, Mr. Vellonakis, the Washington Square Fountain is already aligned. As is, Fountain is Park’s midpoint. June 2, 2008

* What’s happening with Phase II-B / Chess Plaza & SW End? August 31, 2011

* Part I: Washington Square Park Phase II: An Eerie Silence — What’s Going On? September 1, 2010

* Part II: Washington Square Park Phase II: Lack of Transparency and Oversight Continue September 7, 2010

* Part I: Community Board 2 and NY City Council Disavow Oversight of WSP Redesign Project as Phase II Construction Stalled for Five Weeks October 18, 2011

Photo: J. Bary

Spread the love

3 thoughts on “Among Other Things, Phase II Contractor Confirms WSP Fountain is Not Aligned with the Arch After All (Part II)”

  1. It should be emphasized, again, that the community strongly opposed the digging up and moving of the fountain in Washington Square Park. It turns out that the “need” to align the fountain with the arch was an excuse used by the Parks Department and its designer to change the entire character of the park and reduce public space.

    The City claims that the amount of public space in the Park has not been reduced, when one takes into account the grassy areas. But during the recent Occupy Wall Street gathering in Washington Square Park, the fountain and those grassy areas were fenced off (I prefer the term “enclosed”). The Parks Dept. covered the floor of the fountain with a couple of inches of dirty water so that the protesters could not use it to meet, even though in the past hundreds of other speakers, entertainers, and rallyers have used that fountain as an amphitheater.

    One might also note that leaving a layer of stagnant water in the fountain provides a huge breeding ground for mosquitoes. The NYC Department of Health has been fining home-owners for failure to clear standing water from their property. And yet, here we find the Dept. of Parks sabotaging that effort while receiving no fines or even reprimand from the Dept. of Health.

    The issue over the park’s reduction in public space is not so much a claim over the absolute square footage, but over the Parks Department’s and NYPD’s ability to control of that supposedly free space. Control over the space was the real reason behind the City’s “take no prisoners” approach to moving the fountain, come hell or high water.

    Mitchel Cohen
    Brooklyn Greens/Green Party,
    Coordinator, No Spray Coalition, and
    Chair, WBAI (99.5 FM) Local Station Board*

    *for ID purposes only.

    Reply
  2. Great thoughts Mitchel and summing up of the situation. Thanks. Will definitely use that summation in a future post on this topic.

    Um, uptownmanJacob, sorry to bore you. Did you read the post in full, and, if that didn’t clarify why this was important, perhaps Mitchel’s insightful comment above yours would?

    And fyi the “folks down on Wall Street” are also AT Washington Square daily.

    best,
    Cathryn