Part I: Community Board 2 and NY City Council Disavow Oversight of Washington Square Park Redesign Project As Phase II Construction Stalled for Five Weeks

Amended sign- Completion Date: "Or whenever... zzz"

On September 29th, I wrote about how construction on the SouthWest Quadrant/Chess Plaza at Washington Square Park had been stopped for about 3 weeks. 5 weeks passed with no movement or signs of life on this last piece of long overdue Redesign: Phase II work. At this point, delays in the project do not surprise me. Why this is happening is due to a dispute between the Parks Department and the contractor (more on that later).

What does surprise me is the lack of oversight by just about everyone you’d expect to be monitoring this project.

Let’s review the players —

Washington Square Park Task Force

There IS a Washington Square Park Task Force – although you’d never know it – this body seemed to dissolve once City Council Member Alan Gerson left office – replacement Margaret Chin has been totally MIA on the project. Community Board 2 has pretended that the Task Force doesn’t exist and Council Speaker Christine Quinn has not prompted it to keep going. The body was part of the “Gerson-Quinn Agreement,” created for the express purpose of giving the community an opportunity to provide oversight on the project and monitor work on the park’s redesign. In March of 2010, I wrote a piece about how the only way the Task Force would function properly is if it was separated from Community Board 2. Clearly, that remains accurate.

Community Board 2

Trees are dying, work is stopped, project is months behind schedule, budget continues ballooning, something is wrong with the Fountain … and yet Community Board 2 has only chimed in – with regards to WSP in the last year – when they sent out Bob Gormley to talk to the media about the bathroom hours being cut.

Brad Hoylman is back after a 2 year hiatus as Chair of the Board (CB2 chairs only serve 2 year terms). Some may have mixed feelings on his role in the negotiations for the park’s redesign years prior, and he does, after all, work for pro-Bloomberg entity, Partnership for New York City. My experience was that he was pretty decent at moving things along and bringing up and addressing issues during the period I first became involved (2008).

However, since Hoylman returned in June of this year, there’s been no progress or spotlight on the park by the board. He’s left Parks Committee chair Tobi Bergman in charge. As I’ve mentioned, Bergman is a former Parks Department employee who doesn’t take a very hard look at anything related to the Parks Department (in fact, his current job is somewhat dependent on the city agency).

NY City Council

No involvement at all. Council Member Margaret Chin’s office completely unresponsive. Council Speaker Christine Quinn – who was a huge part of the “Gerson-Quinn Agreement” – is hands off at this point but, then, she’s not being pushed to be involved by the bodies that ought to be doing so – the Community Board and Task Force.

We know that the Parks Department is a dysfunctional agency, and so, at this point, this is a project run amok.

************************************************
An Overview:

Phase II Original completion date: Fall 2010. Work was split into two parts earlier this year — Phase II-A (eastern end) opened June 2nd. Budget for all three phases of the park’s elaborate redesign was $16 Million – that figure has now doubled.

************************************************

Previously on WSP Blog: Has Phase II just stopped? September 29, 2011

Spread the love

1 thought on “Part I: Community Board 2 and NY City Council Disavow Oversight of Washington Square Park Redesign Project As Phase II Construction Stalled for Five Weeks”

  1. The job of the NY City Counsel is to take the taxpayer dollars out of the kitty and give them to the Parks Department who gives them to the contractor who hands out the kick backs. Once they have played their part, the members of the City Counsel have absolutely no interest in what happens with construction or if it even happens at all.